On September 24, Huizhou Huiderui Lithium Battery Technology Co., Ltd. released its Investor Relations Activity Record. The first phase of the company's Shexi plant has been planned and constructed with eight production lines, including four cylindrical and four pouch primary lithium battery production lines.
After officially commencing trial production and operation in March 2026, and following an initial period of capacity ramp-up, the monthly production capacity of cylindrical primary lithium batteries at the Shexi plant had exceeded 5 million cells as of the end of June 2026, effectively alleviating the previous tight production capacity situation for certain products. The pouch production lines have also completed small-batch trial production and are currently undergoing product testing and verification. The release of the newly added production capacity at the Shexi plant will need to be carried out gradually in light of market development and order conditions. Investors are advised to be mindful of investment risks.
Edited by Cassie Li, lixiangying@mysteel.com