$3.7B Kurri Kurri Data Centre to transform former aluminium smelter site with 550.5 MW power demand

Source: AL Circle Oct 22, 2026 15:35
Share this with
X linkedin WeChat Copy this link
Aluminum Global Industry

A proposed AUD 3.7 billion data centre at the former Hydro Aluminium Kurri Kurri industrial site in New South Wales, Australia, could repurpose a major industrial property for digital infrastructure, with an estimated peak construction workforce of 1,210 people and around 254 ongoing jobs.

 

The Kurri Kurri Data Centre project, proposed at Hart Road, Loxford, is seeking approval for the fit-out and operation of a large-scale data storage facility with a planned power consumption of 550.5 megawatts (MW). The development application, listed as a State Significant Development under reference SSD-128819490, is currently at the public exhibition stage.

 

The proposal highlights how former aluminium industry sites could find new uses as demand for data storage and computing infrastructure expands.

 

47,143 sqm facility planned for former aluminium industrial site

The proposed development would convert an already approved, two-storey industrial building into a data centre with a gross floor area of 47,143 square metres (sqm).

 

The planned facility would comprise approximately:

  • 32,297 sqm of technical data halls for data storage and computing infrastructure.
  • 1,481 sqm of ancillary office space.
  • 13,365 sqm of corridors and other supporting areas.

The building envelope, with a maximum height of 17.84 metres, and associated earthworks have already received approval through a separate Complying Development Certificate. The current application focuses on the internal fit-out, operation and additional infrastructure required to run the data centre.

 

The overall site covers 20.91 hectares, providing space for the proposed facility and its supporting electrical and cooling infrastructure.

 

550.5 MW power demand and extensive supporting infrastructure

Power supply and cooling will be central to the operation of the proposed data centre. The development plan includes 312 air-cooled chillers, lithium-ion battery storage, six backup diesel generators, an electrical switchyard and two substations.

 

The facility would connect to the Ausgrid electricity network through a dual 132-kilovolt (kV) connection.

 

The proposed data centre is designed to operate around the clock, seven days a week. Its planned power consumption of 550.5 MW makes electricity infrastructure a key component of the project.

 

Air cooling forms part of the proposed infrastructure, while battery storage and backup diesel generators are also included in the development plan. The available project information does not specify the proposed battery capacity, generator ratings or the data centre's anticipated annual electricity consumption.

 

1,210 construction jobs and 254 ongoing positions

The project's employment outlook is another significant element of the proposal. The Environmental Impact Statement estimates that construction and fit-out would take 14 months, with a peak workforce of 1,210 personnel.

 

Once operational, the data centre is expected to support approximately 254 full-time-equivalent positions.

 

These figures distinguish the temporary workforce required to deliver the development from the ongoing employment associated with operating the facility. However, the estimates remain part of the proposed project's assessment rather than confirmed employment outcomes.

 

Development application awaits assessment

ADW Johnson Pty Ltd lodged the development application, while Willowtree Planning was responsible for preparing the Environmental Impact Statement. The project is identified as the Kurri Kurri Data Centre and falls within the Cessnock City local government area.

 

The application is currently listed as being on exhibition, allowing the proposal to proceed through the relevant planning assessment process. The building envelope and earthworks have separate approval, but the current application seeks consent for the data centre's internal fit-out, operation and associated infrastructure.

 

The project's application number, SSD-128819490, can be used to locate the proposal through the New South Wales Department of Planning, Housing and Infrastructure.

 

Note: This article is published in accordance with an article exchange agreement between Mysteel and AL Circle.

You May Also Like
  • VMI Group raises aluminium winding wire capacity to 25,000 TPA

    Oct 15, 2026 15:29

  • Germany's aluminium FRP consumption reaches 1.68 Mt as 2025 trade surplus tops $3.1 billion

    Oct 12, 2026 15:48

  • EU Parliament backs wider CBAM scope for steel and aluminium products

    Sep 16, 2026 17:32

  • Europe's aluminium extrusion demand set to grow at 2.42% CAGR through 2035 - Which end-use sectors will drive it?

    Aug 28, 2026 14:40

  • Southeast Asia's aluminium extrusion boom: Five new projects and 8.47% CAGR - what's driving the growth?

    Aug 07, 2026 15:32

Price Curve
Daily Prices
  • 6063 aluminum billet (Ф120) prices: China's major regions

    Oct 23, 2026 11:58

  • 6063 aluminum billet (Ф90) prices: China's major regions

    Oct 23, 2026 11:58

  • 6063 aluminum billet (Ф178) prices: China's major regions

    Oct 23, 2026 11:58

  • Aluminum billet prices: Wuxi

    Oct 23, 2026 11:57

  • Aluminum prices: China's major cities

    Oct 23, 2026 11:54

Terms & Conditions Privacy Policy Contact Us Mysteel.com
©2026 Mysteel Global Pte. Ltd. All rights reserved. ICP BeiAn No. 沪ICP备15006920号-6
Mysteel Global WhatsApp business account
Customer Service: globalsales@mysteel.com