Chubu Steel Plate halts operations after explosion
Preliminary reports suggest a steam explosion occurred in the slag processing facility at the works which blew out part of the steel shop's roof and walls. The company has suspended operations to conduct safety checks and probe the cause of the accident but says that its plate-rolling operations were unaffected and that rolling operations will continue using stockpiled slabs.
"Shipments will not stop immediately," business daily the Nikkei quotes the company as saying on Wednesday.
The plant, located in Nakagawa in Nagoya, is the company's only works. At an analysts' meeting in August, the company had said it hopes to sell 600,000 tonnes of slabs and plates this year. During its current mid-term business plan that ends next March, the company had targeted 800,000 tonnes/year in sales.
The 200-tonne EAF at the Nakagawa works, commissioned in October 2024, is one of the largest in Japan so an extended shutdown would impact both the company and the scrap market in central Japan, Mysteel Global notes. Chubu Steel Plate has suspended receipt of all scrap deliveries to the works from November 25 for an indefinite period.
Tuesday's was the second steam-explosion accident the company has suffered in two years. On January 21 last year, molten steel had leaked from a fault in the EAF and reacted with water accumulated in the EAF's underground pit, causing an explosion that kept the steel shop offline for over two months until March 30. Rolling operations had commenced in mid-March using slabs supplied by blast furnace makers.
Another company taking a keen interest in progress in recovering the Nagoya plant will be Nakayama Steel Works, a flat products re-roller located in suburban Osaka that has an alliance with Chubu Steel Plate for slab supplies. Nakayama is close to Nippon Steel – the two have an EAF project in train – so availability of slabs shouldn't be an issue. But Nakayama recently had similar bad luck.
On September 12, a fire had broken out on the hot strip and plate mill of its Funamachi works in Osaka that had damaged cables to the heating furnace and other facilities. The company finally restarted operations on October 17. At a business results announcement on November 5 for this year's April-September half, Nakayama announced an ordinary loss of Yen 182 million ($1.2 million) compared with a profit of Yen 2.9 billion in the same period a year ago.
Nakayama blamed surging ferrous scrap prices, delays in passing steel price increases on to customers, and production cuts resulting from the fire at Funamachi.
Written by Russ McCulloch, russ.mcculloch@mysteel.com
Edited by Alyssa Ren, rentingting@mysteel.com
Korea's Daehan Steel to halt Sinpyeong rebar mill
Nov 19, 2026 13:45
Japan's JFE lifts typhoon loss estimate
Nov 10, 2026 09:15
Japan's crude steel output dips in Sept, typhoons a cause
Oct 26, 2026 09:45
Second strike at POSCO another nonevent
Sep 20, 2026 11:45
Titanium concentrates prices: Yunnan
Nov 26, 2026 07:07
Stainless round billet prices: Wenzhou
Nov 26, 2026 06:43
300-series stainless round bar prices: Huzhou
Nov 26, 2026 06:39
300-series stainless wire rod prices: Foshan
Nov 25, 2026 23:18
Mysteel Iron Ore Index
Nov 25, 2026 19:20