According to information released by the Lanzhou Municipal Bureau of Industry and Information Technology on March 2, the commissioning ceremony for Phase I of the annual 100,000-tonne lithium-ion battery cathode material production project by Gansu Jinlin Lithium Battery New Material Co., Ltd. was recently held in Lanzhou New Area.
It is reported that the project covers a total area of 363 mu (approximately 59.5 acres) with a total investment of Yuan 3.135 billion. The project is being constructed in two phases, each with a capacity of 100,000 tonnes. Construction on the Phase I production line, designed to produce 100,000 tonnes of LFP annually, began in April 2024 and officially commenced production after over a year of construction. The Phase II production line, also with an annual capacity of 100,000 tonnes of LFP, is scheduled to begin construction in March 2026.
Edited by Cassie Li, lixiangying@mysteel.com