The Yulong Island crude pipeline construction project has made progress with the commencement ceremony of the Longkou section in East China's Shandong province.
The project will see the construction of a new crude oil pipeline with a length of approximately 105km, a design capacity of 20 million tonnes/year, a pipeline diameter of 711mm, and a design pressure of 8MPa.
Additionally, two new crude oil transmission stations and six pipeline valve chambers will be built.
This project is a supporting project for the Yulong Island Refining and Chemical Integration Project and will ensure a stable supply of raw materials for Shandong Yulong Petrochemical industrial base.
Yulong Island Refining and Chemical Integration Project Progress Review
Time | Progress |
Mar-22 | Publicized the Land Use Planning Permit for the supporting tank farm project outside Yulong island |
May-22 | 2# 1.5 million t/y ethylene unit started constructurion |
May-22 | Chemical tank farm started construction |
Jun-22 | 0.6 milion t/y ABS unit project started consrtuction |
Aug-22 | The first foundation project of the coal-to-gas combined hydrogen production PSA unit was successfully poured |
Sep-22 | The environmental impact assessment documents of the high-end downstream industrial chain extension project of Shandong Yulong Petrochemical were accepted |
Oct-22 | Conducted in-depth communication on the construction of coal-to-gas combined hydrogen production PSA unit |
Oct-22 | Held a 0.15 million t/y maleic anhydride unit process review meeting |
Oct-22 | Shandong Yulong Petrochemical Oil Refining Project completed concrete pouring |
Oct-22 | The main body of the crude oil storage tank farm outside Yulong Petrochemical Island was capped |
Nov-22 | The safety pre-evaluation project of Yantai Port West Port Area–Longkou Yulong Island Oil Pipeline passed the expert review |
Nov-Dec-22 | The residual oil hydrogenation reactor completed construction |
Dec-22 | 1# 1.5 million t/y ethylene unit rectification tower was successfully hoisted |
Jan-23 | 2.6 million t/y naphtha hydrogenation unit started construction |
Feb-4-23 | The storage and transportation 7-1 bid section of the chemical tank farm project started construction |
Feb-17-23 | The quadruple heat exchanger of 0.5 million t/y ethylbenzene/styrene unit completed shipment |
Feb-23 | 2# propylene rectification tower was successfully hoisted |
Mar-23 | Yulong Island crude oil pipeline construction project officially started |